Duct run quantity planner
Build a transparent procurement quantity from your measured route sections and specified duct stock.
Quantity planning only
Use the final agreed design and product schedule for duct size, type, route and interfaces. This tool does not select a design, cable rating, trench depth or safe excavation method. Plan, locate buried services and excavate safely as separate work; see HSE HSG47.
Route sections
Enter one named section per specified stock length and allowance basis.
Enter route and stock details. Empty fields are not treated as zero.
No entries are stored. Export before leaving if you need a copy.
How the quantity is allocated
For each named section, enter the measured length of one route run, the number of parallel ducts and the straight stock length shown in the project schedule. This planner uses a no-sharing allocation boundary: it applies the entered allowance to each individual parallel run, rounds that run up to whole stock lengths, then multiplies by the parallel duct count. Offcuts are not transferred between runs or sections.
Allowed length per run = measured length × (1 + allowance ÷ 100)
Stock lengths per run = round up (allowed length ÷ specified stock length)
Section stock count = stock lengths per run × parallel duct count
Fitting fields are separate counts copied from your specified arrangement. The tool does not infer bends, couplers or chamber interfaces from route length, spacing or a universal assumption.
Worked example
For a fictional section named East route, enter 23.4 m of physical route, 3 parallel ducts, 3 m stock and a declared 5% length allowance. That is 70.2 duct metres before allowance. The allowed length per run is 24.57 m. Dividing by 3 m gives 8.19, rounded up to 9 stock lengths per run. At this allocation boundary the section quantity is 27 whole lengths, or 81 m of stock. Add only the bend, coupler and chamber-interface counts shown by your own arrangement.
These figures demonstrate arithmetic only. The stock length and allowance are example inputs, not product recommendations or standard values.
Use the project design for specification and interfaces
Enter sections from the final agreed route and product schedule. For a UK Power Networks connection, its published duct guidance says details are to follow the agreed design and approved size and type for that connection; this is network-specific guidance, not a UK-wide rule. Confirm the applicable network owner's requirements for your project.
This schedule does not determine whether sections can share stock, account for cuts or jointing constraints, select accessories, set a route, or check clashes. Verify quantities and interfaces against current drawings, schedules, supplier information and package boundaries before ordering. The pipe bedding and trench calculator covers a different task: drainage trench and granular material quantities.
Related resources
Aggregate & MOT Type 1 tonnage calculator
Work out the tonnage of MOT Type 1, sub-base, capping, sand, gravel, or topsoil by area and depth, with typical UK bulk densities, bulk-bag, and tipper-load counts.
Concrete specification quick reference for site
Application selector, exposure classes, cover depths, reinforcement weights, and slump guidance. Everything from BS 8500 that a site agent needs on one page.
Concrete volume calculator & mix selector
Work out concrete volume by shape, get an indicative BS 8500 strength class, a wastage allowance, and a ready-mix truck count for a UK pour.