Skip to main content
A commercial manager in lime hi-vis reviewing a construction valuation and payment diary at a site office desk

Construction payment date calculator

Start from the contract's payment trigger, then calculate the four dates that control when notices are served and money must arrive.

Updated

Share

A valuation records what completed work is worth at a point in time. An assessment is the contract administrator's calculation of the amount due. A claim is the payee's written request for payment, stating the amount and how it was calculated. The payee receives the money; the payer pays it.

Construction payment dates are a chain, not a single deadline. The due date fixes when a sum is assessed as due. A payment notice states the sum and calculation. A pay less notice is the payer's last notice for reducing the notified sum, meaning the amount established by the applicable payment notice. The final date for payment is when the applicable sum must be paid.

Payment timetable calculator

Choose the closest starting template, enter the dates, then replace every interval with the wording in your signed contract.

Starting template

The last day of the relevant period used by your payment cycle.

The date the payee gives a written claim stating the amount and basis.

Intervals from the contract

The statutory Scheme intervals are locked. Choose JCT, NEC4 or your contract to enter different terms.

Enter the dates above to calculate the timetable.

What each template calculates

The selected calculator template is highlighted. JCT and NEC4 are starting points only, because amendments and Contract Particulars, the project-specific entries completed in a standard contract, can change the intervals.

Scheme for Construction Contracts

For a periodic payment, the due date is the later of seven days after the relevant period and the date the payee makes a written claim. The default final date is 17 days after due. If the contract does not specify the relevant period, the Scheme defines it as 28 days.

Payment notice: due + 5 days. Pay less: final date minus 7 days. Scheme Part II, paragraphs 4 and 8 to 10.

JCT SBC interim payment example

The official JCT explanation of SBC/Q 2016 uses an Interim Valuation Date (IVD), then due +7 days, final +14 days and pay less no later than five days before final.

Confirm the edition, contract form, IVD and any schedule of amendments, meaning a separate document that changes the standard wording. JCT interim payment guidance.

NEC4 invoice-linked Y(UK)2 example

The October 2020 amendments for PSC, TSC and DBOC use the later of invoice receipt and assessment +14 days as due, with final +7 days unless Contract Data states another period.

NEC4 subcontracts and other NEC forms can use different periods. Read the exact Y(UK)2 clause and Contract Data. NEC Contracts Y(UK)2 explanation.

Your contract

Use a known reference date and enter the due, payment notice, final payment and pay less intervals exactly as written in the signed contract.

If the mechanism is missing or non-compliant, only the relevant Scheme provisions may be implied.

The four dates in the payment chain

Select any result above to highlight its meaning here.

1. Due date

This is when the payment becomes due under the contract. It is not necessarily the day cash must arrive. Section 110 requires an adequate mechanism for determining what becomes due and when.

2. Payment notice

Section 110A requires the contract to provide for a notice stating the sum considered due and the basis of calculation. The statutory longstop is no later than five days after the due date.

3. Pay less notice

This notice states the lower sum the payer considers due and its calculation. It must be served within the contract's prescribed period, or seven days before final payment where the Scheme supplies the period.

4. Final date for payment

Section 111 requires the notified sum to be paid by this date unless a valid pay less notice changes the applicable amount. If the payer fails to issue its required payment notice, section 110B lets the payee issue a replacement notice. When that replacement is given after its permitted date, the final date moves by the same number of days as the replacement notice was late.

Before relying on a date

  • Check the jurisdiction. The Scheme template here is for England and Wales. Scotland and Northern Ireland have separate schemes and legislation.
  • Identify the exact contract and amendments. A schedule of amendments can replace the printed intervals in JCT or NEC4.
  • Check what starts the clock. An application date, Interim Valuation Date, assessment date, invoice receipt and relevant period end are not interchangeable.
  • Read the service clause. Email cut-off times, deemed receipt, the contract's rule for when a message counts as received, weekends and public holidays can change when a notice is treated as served.
  • Account for a default notice. If the payer misses its required payment notice and the payee gives the section 110B replacement after the date it was first permitted, the final date moves by the same number of days as that replacement was late.

This calculator is a diary aid, not legal advice or a decision that a notice is valid. Get contract-specific advice before withholding payment, suspending work or starting adjudication, the fast statutory dispute process available for construction contracts.

Sources

Share

Related resources

Send an enquiry

Request a callback

We'll call you back during work hours (Mon-Fri, 9am-5pm).