# Temporary dewatering readiness checklist

> Record the evidence and unresolved conditions for temporary excavation dewatering in England, without treating RPS 261 as a permit approval.

- Canonical HTML: https://rospower.co.uk/resources/temporary-dewatering-readiness-checklist/
- Documentation index: https://rospower.co.uk/llms.txt
- Updated: 2026-09-23

> This Markdown version contains the published explanatory content. Use the canonical HTML page for calculators, builders and other interactive controls.

## Page content

An England-only evidence worksheet for a proposed temporary excavation discharge. It records gaps and escalation actions, not permission to pump.

## This is not permission to pump

RPS 261 does not change the legal requirement to obtain a water discharge activity permit for a short-term temporary discharge of uncontaminated water from an excavation to surface water. The Environment Agency says it will not normally take enforcement action only where the activity matches the RPS, every condition is met, and there is no actual or likely pollution or harm to human health.

A completed worksheet is an evidence record only. It does not approve a permit, decide whether a permit is needed, approve a pumping design or authorise discharge.

## Evidence worksheet

The worksheet stays in this browser. It does not save, upload or share answers.

Readiness is incomplete because one or more answers are unknown. Unknown is not an affirmative answer. Do not use this worksheet to authorise pumping or to treat a permit as approved.

Affirmative evidence

0

Unknown or incomplete

26

No or failed condition

0

### Activity scope and permit triggers

Answer yes only where the project evidence supports the statement. A no or unknown needs action.

### Conditions to evidence

These prompts record the operational controls required by RPS 261.

### Exclusions and receiving-water checks

These exclusions need evidence before a temporary discharge is considered further.

### Records and recheck

Keep the decision trail with the work package, not only in this browser.

### Separate abstraction question

RPS 261 only concerns the discharge activity. It does not decide the abstraction route.

### Unresolved actions

Each unknown or no answer remains here until evidence or a competent decision changes the answer. This list is not a permit decision.

## RPS 261 limits that remain visible

- **Receiving water:** the RPS is for surface water only. It does not apply to ground or groundwater discharges.
- **Three-month clock:** a pause does not reset the three consecutive month period. If it is likely to go over, the RPS directs the operator to apply for a water discharge activity permit.
- **Protected sites:** do not discharge within, or less than 500 metres upstream of, the RPS list of protected habitats and conservation sites. The list includes SSSI, SAC, SPA, Ramsar, marine conservation zones, ancient woodland, national and local nature reserves and local wildlife sites.
- **Separate abstraction route:** dewatering may require both an abstraction licence and a water discharge activity permit. More than 20 cubic metres a day is a separate licence trigger in the linked guidance, subject to any applicable exemption or RPS. This worksheet does not interpret those exceptions.
- **If compliance is lost:** stop the activity and tell the Environment Agency immediately, using RPS 261 in the subject line.

## Sources and recheck record

- [Temporary dewatering from excavations to surface water: RPS 261](https://www.gov.uk/government/publications/temporary-dewatering-from-excavations-to-surface-water-rps-261/temporary-dewatering-from-excavations-to-surface-water): England-only source for the activity description, every condition and exclusion, record retention, three-month limit, protected-site distance, abstraction note, review and stop-and-notify instruction. Page checked 23 September 2026, and shown as updated 23 April 2026.
- [Get advice before you apply for an environmental permit](https://www.gov.uk/guidance/get-advice-before-you-apply-for-an-environmental-permit): Environment Agency pre-application advice can help scope a proposal, but does not confirm that no permit is needed or that a proposal will be approved.
- [Apply for a water abstraction or impounding licence](https://www.gov.uk/guidance/water-management-apply-for-a-water-abstraction-or-impoundment-licence) and [RPS 368 for small-scale construction dewatering abstractions](https://www.gov.uk/government/publications/small-scale-abstractions-for-construction-dewatering-rps-368): separate abstraction materials linked from RPS 261. They need a separate check against the actual proposal.

The Environment Agency may amend or withdraw RPS 261 before its stated review date of 30 April 2028. Recheck the live source immediately before use.

Related guidance

- [Temporary works checklist](https://rospower.co.uk/resources/temporary-works-checklist/)
- [SuDS compliance guide](https://rospower.co.uk/resources/suds-compliance/)
- [Drainage gradients and falls](https://rospower.co.uk/resources/drainage-gradients/)
- [Underground services safe digging](https://rospower.co.uk/resources/underground-services-safe-digging/)
- [Work with Rospower Projects](https://rospower.co.uk/work-with-us/)