# Kerb quantity estimator

> Estimate straight kerb units from measured runs, openings, the specified product length and an allowance entered by the user.

- Canonical HTML: https://rospower.co.uk/resources/kerb-quantity-estimator/
- Documentation index: https://rospower.co.uk/llms.txt
- Updated: 2026-10-14

> This Markdown version contains the published explanatory content. Use the canonical HTML page for calculators, builders and other interactive controls.

## Page content

Turn measured straight runs into an estimated unit count using your product schedule and project-specific allowance.

## Estimate only, not a setting-out or design tool

Use straight lengths and the unit length from the selected product schedule. Curves, transitions, returns, corner units, cutting plans, breakage and reuse of offcuts need separate project quantities. The allowance is your input, not a recommended percentage.

## Enter each straight run

Use the same product length and unit of measure within each run. Add separate rows for different products or areas.

Enter a run length and the straight unit length from your product schedule.

Download includes your inputs and references. Entries are not stored; save a copy before leaving.

## How the estimate works

For each run, the estimator subtracts the deductions you enter from the measured straight length. It divides the net length by the scheduled straight unit length and rounds up to a whole unit. If you enter an extra allowance, the tool rounds that allowance up to whole units as well.

**Net length = measured run - deductions** **Base units = round up (net length / unit length)** **Estimated total = base units + round up (base units x allowance / 100)**

Each row is rounded separately. The result does not assume that offcuts can be reused between runs, or that a specified percentage covers every corner, curve, damaged unit or installation condition. Enter a measured straight run and a unit length taken from the actual project schedule. No default product size is assumed.

### Worked quantity example

Suppose you measure a 12 m run with a 1.2 m opening and enter a 0.915 m straight unit from a fictional product schedule. You have 10.8 m to cover: 10.8 / 0.915 = approximately 11.80, rounded up to 12 units. If you enter 5% extra, the allowance is 0.6 units, rounded up to one. The estimate is 13 straight units.

These are example inputs, not a standard size or recommended allowance. You still need to schedule specials and confirm cuts, joints and the supplier's product dimensions separately.

## Keep non-straight details separate

Returns, radii, dropped kerbs, transitions, specials and corner units may use different products or installation rules. Measure and schedule them separately rather than forcing them into a straight-run calculation. Confirm openings and interfaces with the current drawing before ordering. This page does not set kerb lines, levels, restraint, bedding or concrete details.

## Check the order against the work area

Use the result as a quantity cross-check, then compare it with the approved drawings, product schedule, package scope and supplier's unit length. Keep each row tied to its area and product reference. A total number of straight units does not establish that the layout is buildable or that the correct kerb type has been selected.

For sequencing around channels, gullies and surfacing, read [kerbs before asphalt](https://rospower.co.uk/blog/kerbs-before-asphalt/). For concrete properties and terminology, see the [concrete specification guide](https://rospower.co.uk/resources/concrete-specification/).

Related guidance

- [Kerbs before asphalt](https://rospower.co.uk/blog/kerbs-before-asphalt/)
- [Concrete specification guide](https://rospower.co.uk/resources/concrete-specification/)
- [HGV yard compaction records](https://rospower.co.uk/blog/hgv-yard-compaction-records/)
- [Work with Rospower Projects](https://rospower.co.uk/work-with-us/)