# Groundworks inspection and test plan builder

> Build an editable groundworks inspection and test plan with activity stages, point types, responsibilities, acceptance criteria and evidence records.

- Canonical HTML: https://rospower.co.uk/resources/groundworks-itp-builder/
- Documentation index: https://rospower.co.uk/llms.txt
- Updated: 2026-10-07

> This Markdown version contains the published explanatory content. Use the canonical HTML page for calculators, builders and other interactive controls.

## Page content

Turn controlled project information into practical inspection stages, point types, responsibilities and records before work is covered.

**An inspection and test plan (ITP)** states what will be checked, when it will be checked, who is responsible, what evidence will be retained and whether work must pause for release. This builder gives you an editable starting structure. Your contract, drawings, specifications, approved methods and quality plan control the final entries.

It does not set universal test frequencies, tolerances or acceptance values. Confirm every row with the designer, client or named acceptance authority before using it on a project.

## Build the project ITP

Edit the common stages, hide packages that are outside your scope, add project-specific rows, then print or download a CSV working copy.

Visible rows

10

Hold points

7

Witness points

1

Review points

2

| No. | Activity | Precondition | Inspection or test | Acceptance criterion | Point | Responsible | Record | Action |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| 1 |  |  |  |  |  |  |  |  |
| 2 |  |  |  |  |  |  |  |  |
| 3 |  |  |  |  |  |  |  |  |
| 4 |  |  |  |  |  |  |  |  |
| 5 |  |  |  |  |  |  |  |  |
| 6 |  |  |  |  |  |  |  |  |
| 7 |  |  |  |  |  |  |  |  |
| 8 |  |  |  |  |  |  |  |  |
| 9 |  |  |  |  |  |  |  |  |
| 10 |  |  |  |  |  |  |  |  |

The builder works in this browser only. Nothing is uploaded or stored.

## Define the point types before work starts

These labels are common, but their contractual effect varies. Record the notice period, release authority and proceed rule in the agreed quality plan.

### Hold point

Work does not continue beyond the stated stage until the named authority records release. Define who can release it and what evidence they need.

### Witness point

The named party is notified and given the agreed opportunity to attend. State what happens if they do not attend, because contracts use different proceed rules.

### Review point

A document, result or record is reviewed at the stated stage. Define whether acceptance is needed before the activity proceeds or whether review can follow.

## What every useful row needs

### A locatable activity

Name the area, layer, run, pour or drawing zone. A broad line such as groundworks complete cannot be traced later.

### Controlled criteria

Reference the actual drawing, specification clause, approved method or schedule. Do not import a tolerance from another project.

### Named responsibility

Separate the person who performs the check from any client, designer or principal contractor authority needed for release.

### A retrievable record

State the form, drawing, test result, survey, photograph or certificate and how it connects to the inspected location.

Planning a drainage inspection and recording its result are separate steps. Use the [drainage test record builder](https://rospower.co.uk/resources/drainage-test-record-builder/) to connect an individual test to the asset, actual readings, project criteria, evidence and reviewer decision. The record does not choose the test method or make an automatic pass decision.

## Limits and safety boundaries

### Quality plan, not risk assessment

An ITP does not replace the construction phase plan, risk assessments, permits or method statements. Link the documents where they control the same activity.

### Project criteria control

The common rows are prompts only. Test methods, frequencies, tolerances and acceptance decisions must come from the project design and contract.

### Record work before covering

Set points where evidence can still be checked and defects can still be corrected. A photograph after backfill cannot prove the hidden installation.

### Close non-conformance clearly

Link a failure to its location, corrective action, retest or accepted disposition. Do not leave an isolated result without the decision that closed it.

## Sources and further guidance

- [Planning for construction work](https://www.hse.gov.uk/construction/safetytopics/planning.htm): HSE explains the information, roles and construction phase planning required before work starts.
- [Construction administration](https://www.hse.gov.uk/construction/safetytopics/admin.htm): HSE distinguishes statutory plans, inspection reports, risk assessments and method statements.
- [HSG47 avoiding danger from underground services](https://www.hse.gov.uk/pubns/books/hsg47.htm): planning, locating services and safe excavation controls.
- [Excavation safety and inspection](https://www.hse.gov.uk/construction/safetytopics/excavations.htm): HSE guidance on competent inspection, reports and corrective action.
- [Manual of Contract Documents for Highway Works](https://www.standardsforhighways.co.uk/mchw): use the version and works-specific requirements specified by the project contract, not automatically the latest edition. MCHW does not apply to every private groundworks project.

Related guidance

- [HGV yard compaction records](https://rospower.co.uk/blog/hgv-yard-compaction-records/)
- [Temporary works checklist](https://rospower.co.uk/resources/temporary-works-checklist/)
- [Underground services safe digging](https://rospower.co.uk/resources/underground-services-safe-digging/)
- [Effective project management](https://rospower.co.uk/blog/effective-project-management/)
- [Work with Rospower Projects](https://rospower.co.uk/work-with-us/)