# EV charging infrastructure civil works guide

> Reference tool for UK EV charging installations: cable specs, substation thresholds, groundworks scope, and DNO connection timelines by charger power tier.

- Canonical HTML: https://rospower.co.uk/resources/ev-charging-civil-works/
- Documentation index: https://rospower.co.uk/llms.txt
- Updated: 2026-05-15

> This Markdown version contains the published explanatory content. Use the canonical HTML page for calculators, builders and other interactive controls.

## Page content

What civil engineering is involved at each charger power tier. Cable specs, substation thresholds, groundworks scope, and DNO connection timelines for UK installations.

## UK EV infrastructure: 2026 outlook

- • DfT's latest quarterly release reports public EV chargers, not just charging devices, and is correct as of 1 January 2026
- • DfT power bands classify 50kW to less than 150kW as rapid, and 150kW and above as ultra-rapid
- • Rapid and ultra-rapid chargers together account for about 22% of public EV chargers in the January 2026 release
- • MW-class charging for heavy-duty fleets should be treated like an industrial HV connection project, not a car park retrofit
- • Civil engineering scope increases dramatically above 50kW

Source: [DfT public EV charging infrastructure statistics, January 2026](https://www.gov.uk/government/statistics/electric-vehicle-public-charging-infrastructure-statistics-january-2026/electric-vehicle-public-charging-infrastructure-statistics-january-2026)

## Charger tier scope calculator

Select a charger power tier, number of charge points, and site type to see the civil engineering scope.

### Power supply

Total site load200kW

Supply typeThree-phase 80A+

Substation requiredLikely

DNO connection timeline8-16 weeks

### Cable and ducting

Cable type35mm² SWA

Minimum duct size100mm

Trench depth600mm

Utility separation100mm from comms

### Groundworks scope

Foundation typeConcrete plinth

HardstandingStandard car park

DrainageReview existing

Ancillary ductingLighting + CCTV

### Civil works complexity

RatingModerate

Key cost driversDNO connection, trenching, substation compound

Typical civil works duration4-8 weeks

## Site layout reference dimensions

Typical space requirements for different hub sizes. Use as a starting point for feasibility assessments.

### Small hub (4x 50kW)

Site area and bays

- • Minimum site area: ~200m² (parking bays + access)
- • Bay width: 2.7m standard, 3.6m accessible
- • Bay depth: 5.0m (car), 6.0m (with overhang space)
- • Aisle width: 6.0m minimum for two-way traffic

Infrastructure

- • Feeder pillar/switchgear compound: ~4m x 2m
- • Cable run from pillar to furthest bay: typically 20-40m

### Medium hub (8x 150kW)

Site area and layout

- • Minimum site area: ~600m² (bays + island canopy + access)
- • Separate pedestrian access if canopy provided

Infrastructure

- • Substation compound: ~6m x 4m minimum (consult DNO)
- • HV cable route from boundary: varies by site

### Large hub (12x 350kW or HGV depot)

Site area and access

- • Minimum site area: 1,200m²+ for cars, 2,500m²+ for HGVs
- • HGV turning circle: 20m minimum diameter
- • Separate car and HGV access preferred

Infrastructure

- • Substation: 8m x 6m+ (11kV or 33kV)
- • Drainage design for large hardstanding area (SuDS may be required)

## Utility duct specification reference

Standard UK duct colours and separation distances based on NJUG Volume 1 guidelines. Always confirm with the local DNO and utility providers for site-specific requirements.

| Utility | Duct colour | Minimum depth | Min. separation from other ducts |
| --- | --- | --- | --- |
| Electricity (LV) | Black | 450mm (footpath), 600mm (road) | 100mm from comms |
| Electricity (HV) | Red | 750mm (footpath), 900mm (road) | 300mm from LV, 600mm from gas |
| Gas | Yellow | 450mm (footpath), 600mm (road) | 600mm from electricity |
| Water | Blue | 750mm minimum | 350mm from other services |
| Telecoms / data | Green or grey | 350mm (footpath), 450mm (road) | 100mm from electricity |
| EV charging feeder | Black (marked) | 600mm typical | As per LV/HV depending on voltage |

## Regulatory and delivery checklist

0 / 17 covered

Tick off each item as you confirm it for your project. Expand any item for more detail.

### Planning and permissions

### DNO and power supply

### Civil engineering and groundworks

### Accessibility and compliance

## Practical notes

Things to keep in mind when planning EV charging civil works.

### DNO timelines are indicative

Actual timelines depend on existing network capacity, required reinforcement, and DNO workload. In areas where the distribution network is already at capacity, reinforcement works can add 6-12 months to the programme. Request a budget estimate as early as possible.

### Early DNO engagement for HV sites

For sites requiring HV connections (typically 150kW+ hubs), early engagement with the DNO is essential. Budget estimates are free and non-committal. They give you the information needed to make a business case before committing to detailed design. Some ICPs (Independent Connection Providers) can also provide competitive quotes for the connection works.

### OZEV grant schemes

OZEV workplace and on-street grant schemes have specific technical requirements that may affect civil works scope. Eligible installations must meet particular power output, accessibility, and data-sharing criteria. Check [GOV.UK OZEV grants](https://www.gov.uk/guidance/electric-vehicle-chargepoint-grants) for current eligibility and requirements before finalising your civil design.

### PAS 1899:2022 accessibility standards

PAS 1899:2022 sets accessibility standards for public EV charging. If installing public chargers, the civil works (bay sizes, gradients, surface finishes, kerb detailing) must accommodate these requirements from the design stage. Retrofitting accessibility after installation is significantly more expensive than getting it right first time.

## Sources

- [Electric vehicle public charging infrastructure statistics: January 2026](https://www.gov.uk/government/statistics/electric-vehicle-public-charging-infrastructure-statistics-january-2026/electric-vehicle-public-charging-infrastructure-statistics-january-2026) (DfT)
- [Electric vehicle charging infrastructure statistics data tables](https://www.gov.uk/government/statistical-data-sets/electric-vehicle-charging-infrastructure-statistics-data-tables-evci) (DfT)
- [Electric vehicle chargepoint grants](https://www.gov.uk/guidance/electric-vehicle-chargepoint-grants) (GOV.UK)
- [PAS 1899:2022 accessible EV charging points specification](https://landingpage.bsigroup.com/LandingPage/Standard?UPI=000000000030440797) (BSI)

Built by [Rospower Projects](https://rospower.co.uk/). We deliver civil engineering for EV charging infrastructure, renewable energy, and utility connections across the UK.

[Discuss your project](https://rospower.co.uk/contact/)

Related resources

- [Renewable energy & utility projects](https://rospower.co.uk/services/renewable-energy-infrastructure/)
- [Utility connections (NERS)](https://rospower.co.uk/services/utility-connections/)
- [Automotive & logistics facilities](https://rospower.co.uk/services/automotive-logistics-facilities/)
- [Earthworks cut & fill calculator](https://rospower.co.uk/resources/earthworks-cut-fill/)
- [Percolation test & soakaway sizer](https://rospower.co.uk/resources/percolation-soakaway-sizer/)