# Earthworks cut & fill calculator

> Calculate cut and fill volumes, look up soil bulking factors, and estimate disposal tonnage. Built for UK groundworkers and site engineers.

- Canonical HTML: https://rospower.co.uk/resources/earthworks-cut-fill/
- Documentation index: https://rospower.co.uk/llms.txt
- Updated: 2026-10-07

> This Markdown version contains the published explanatory content. Use the canonical HTML page for calculators, builders and other interactive controls.

## Page content

Calculate cut and fill volumes, look up soil bulking factors, and estimate disposal tonnage. Built for UK groundworkers and site engineers.

## Volume calculator

Enter your excavation or fill dimensions to calculate bank, loose, and compacted volumes.

## Bulking & shrinkage reference

Typical values for UK soil types. Use the tabs to switch between cut (excavation) and fill (placement) properties.

| Soil type | Bulk density (kg/m³) | Bulking factor | Loose density (kg/m³) | Tonnes per m³ (bank) |
| --- | --- | --- | --- | --- |
| Topsoil | 1,450 | 1.25 | 1,160 | 1.45 |
| Clay | 1,750 | 1.30 | 1,346 | 1.75 |
| Sand | 1,600 | 1.12 | 1,429 | 1.60 |
| Gravel | 1,850 | 1.12 | 1,652 | 1.85 |
| Chalk | 1,500 | 1.35 | 1,111 | 1.50 |
| Made ground | 1,600 | 1.25 | 1,280 | 1.60 |
| Rock | 2,500 | 1.50 | 1,667 | 2.50 |
Bulking factor = ratio of loose volume to bank volume. A factor of 1.25 means 1 m³ in-situ becomes 1.25 m³ after excavation.

| Soil type | Compaction factor | Compacted density (kg/m³) | Recommended layer thickness | Compaction method |
| --- | --- | --- | --- | --- |
| Topsoil | 0.90 | 1,611 | 150mm layers | Tracked plant or plate compactor |
| Clay | 0.90 | 1,944 | 225mm layers | Sheepsfoot roller |
| Sand | 0.95 | 1,684 | 300mm layers | Vibrating roller |
| Gravel | 0.95 | 1,947 | 300mm layers | Vibrating roller |
| Chalk | 0.85 | 1,765 | 200mm layers | Smooth roller |
| Made ground | 0.85 | 1,882 | 200mm layers | Vibrating roller |
| Rock | 1.30 | 1,923 | 500mm layers | Heavy vibrating roller |
Compaction factor = ratio of compacted volume to bank volume. A factor of 0.90 means 1 m³ of bank material compacts to 0.90 m³ after placement. Rock at 1.30 means it expands when broken and placed.

## Disposal tonnage estimator

Estimate the number of wagon loads needed to remove excavated material from site.

Total tonnage

145.0 t

Bank volume x bulk density

Number of loads

13

Loose volume / vehicle capacity, rounded up

Tip and disposal rates vary by region, waste classification, and tip site. Contact your local tip for current rates.

## CBR reference values

Typical California Bearing Ratio values by soil type. CBR determines suitability as fill and influences pavement design thickness.

| Soil type | Typical CBR range (%) | Suitability as fill | Notes |
| --- | --- | --- | --- |
| Topsoil | 1-3 | Not suitable | Strip and store separately. Cannot be used as structural fill. |
| Clay (stiff) | 3-7 | Acceptable (Class 2) | Moisture-sensitive. May need lime stabilisation below CBR 5. |
| Clay (soft) | 1-3 | Poor | Likely needs removal or treatment. High shrink-swell risk. |
| Sand | 10-20 | Good (Class 1) | Free-draining. Good bearing capacity when confined. |
| Gravel | 20-60 | Excellent (Class 1) | Ideal structural fill. Self-draining. |
| Chalk | 3-8 | Acceptable (Class 3) | Frost-susceptible. Keep below 450mm from surface. |
| Made ground | Variable | Test required | Always test. May contain contaminants. Waste classification needed. |
| Crushed rock | 40-80 | Excellent (Class 6) | Engineered fill. Consistent properties. |
CBR values are indicative. Always verify with site-specific testing, particularly for pavement design and structural fill acceptance.

## Important notes

- • These are typical values. Actual values depend on site-specific conditions and should be verified by ground investigation.
- • All fill placement should comply with the project specification and relevant standards (BS 6031 and National Highways MCHW Series 600 where applicable).
- • Contaminated or hazardous material requires waste classification before disposal. Duty of care applies under the Environmental Protection Act 1990.

A volume or tonnage estimate does not classify spoil or authorise its movement off site. For work in England, our [excavated spoil checks before transfer](https://rospower.co.uk/blog/construction-waste-classification-and-transfer/) guide covers the separate questions about waste status, classification, the receiving site and transfer records.

## Sources

- [BS 6031:2009](https://knowledge.bsigroup.com/products/code-of-practice-for-earthworks) Code of practice for earthworks
- [National Highways standards search](https://www.standardsforhighways.co.uk/search?term=Series%20600) for MCHW Series 600 earthworks specifications
- [GOV.UK: Dispose of hazardous waste](https://www.gov.uk/dispose-hazardous-waste) duty of care and hazardous waste handling guidance

Built by [Rospower Projects](https://rospower.co.uk/). We deliver earthworks and groundworks across the UK.

[Discuss your project](https://rospower.co.uk/contact/)

Related resources

- [Aggregate & MOT Type 1 tonnage calculator](https://rospower.co.uk/resources/aggregate-tonnage-calculator/)
- [Drainage gradients & falls calculator](https://rospower.co.uk/resources/drainage-gradients/)
- [Renewable energy & utility projects](https://rospower.co.uk/services/renewable-energy-infrastructure/)
- [Warehouse & industrial estate groundworks](https://rospower.co.uk/services/warehouse-groundworks/)
- [Our project portfolio](https://rospower.co.uk/projects/)